Viewing workset details
To view workset details:
- Select Warehouse Mobility > > Warehouse Mobility - Hours Accounting > Workset Details.
 - The information for each workset is displayed.
 - Optionally, specify this information:
           
- Time Split Method
 - 
              To determine how time will be split between multiple tasks within a workset, specify one of these:
              
- Simple Average: Divided equally between tasks.
 - Weighted Average: Divided to each task based on its standard duration For example, if job A usually takes 20 minutes to complete and job B usually takes 40 minutes to complete, twice as much time will be allocated to job B as to job A.
 - Quantity Based: Divided to each task based on the quantity produced For example, if task A produces two items and task B produces four items, twice as much time are allocated to job B as to job A.
 
 
- Allow Time Split Method Modification
 - Select to allow users to change the time split method.