Managing Resources

  1. Access the Resources form.
  2. Specify this information:
    Resource ID
    The code of the resource.
    Description
    The description of the resource.
    Resource Parent
    The parent resource to which the resource belongs.
    Description
    The description of the resource parent.
    Can Assign To Job(s)
    Select this check box to directly assign jobs to the resource.
    From ERP
    Indicates whether the resource is synchronized from the integrated ERP.
    Shifts
    The working shift of the resource.
    Status
    The operational status of the resource.
    Resource Type
    The type of resource. Possible value:
    • Labor
    • Machine
    • Other
    Work Area
    The work area of the resource.
    Using Machine Integration
    Select this check box to connect a resource to a machine through machine integration, for capturing the data automatically.
    Machine Server ID
    The machine server ID used for integration.
    Machine Channel
    The channel used to communicate with the machine server.
    Controller Folder Name
    The folder path of the controller who manages machine interface.
    Polling Interval
    The frequency at which the system polls the resource or machine for updates.
    Start From Integration
    Select this check box to start the job from machine integration.
    No Running Job Code
    The downtime code that must be used when a machine is running without an identified job.
    Note: This field is displayed only if the Start From Integration check box is selected.
    Tag Regen Time Interval (Minutes)
    The interval in which the machine tags are regenerated, in minutes.
    Archive Tag Time Interval (Days)
    The interval in which the tags are archived.
    Last Regen
    The date and time when the tags were last regenerated.
    Last Archived
    The date and time when the tags were last archived.
  3. Select the Activity and specify the Tag ID, Tag Name, and Tag Value.
  4. Click Save.