Configuring the parameters on the Calendar Setup tab
To configure parameters:
- Start Date
- The start date of the Site Calendar year.
- Tracking Year
- The year of the site Start Date.
- 1st Day of Work Week
- The first day of the work week. The default value is Sunday.
- Work Week Effective Date
- The start date specified for the Site.Note:
- If the company policy regarding the work week is updated, then the updated date must be specified in this field.
- This date must not be updated during the annual transition.
- Generate Work Week
- The Generate Work Week option creates the Start Date as the first day of the week for all the weekly queries and references.