Receiving Items from Production Schedules

  1. Select Material > Production Schedule Receipt. The Production Schedule Receipt form is displayed.
  2. Specify or review this information:
    Item
    The item you are receiving.
    Schedule
    The production schedule.
    Work Center
    The work center of the production schedule.
    Operation
    The operation of the production schedule.
    Location
    The location for the transaction.
    Note: 
    • This field is defaulted based on the Item stock room location for the transaction.
    • The location is same for both BOM item and the new item issue.
    Shift
    The code of the shift.
    Qty To Receive
    The quantity of items that must be received.
    Document Number
    The document number for the material transaction re-consolidation or grouping in CSI.
    Scrapped Qty
    The quantity of items to be scrapped.
    Note: Positive quantities increase the scrapped item count of the product schedule, and negative quantities decrease the count.
    Scrapped Reason
    The reason code for the scrapped items.
    Container
    Scan a container into which to receive the completed items. Optionally, leave this field blank to generate a new container number.
    Note:  This field is displayed only if the To Container check box is selected.
  3. Clear the Reverse Quantity check box to receive the items.
  4. Select the To Container check box to issue the completed items to a container.
    Note: This check box is displayed only if the Time Track module is not implemented and this is the last operation.
  5. Verify that the item details such as Item Description, Work Center Description, Warehouse, and Location are displayed on the Details tab.
    • Specify a lot number on the Lot/Serial tab, if applicable. The lot number is specified by default.
    • Verify that he quantity of serial numbers that are not assigned are displayed in the Un-Assigned field on the Lot/Serial tab, if applicable. Select the arrow button to assign serial numbers to the items you are receiving. See Assigning Serial Numbers for details. You must assign all unassigned serial numbers to receive the items.
  6. Click Process to receive the items.
    Note: 
    •  If the Print Labels parameter is selected for this transaction, the Label Printing form is opened. See Printing Labels for information about printing labels.