Prerequisites
These prerequisites apply to the AWM module and can be configured by the system administrator.
Specify these profile attributes for AWM:
Profile attribute | Value |
---|---|
APM.ENABLED | 1 |
APM.THRESHOLD | The default value is 5. This value determines when a task is considered to be late. |
Field | Description |
---|---|
Full Elasticity |
If this check box is not selected and a task is completed early or late, Optiva will not automatically re-calculate Start and Due Dates for all upstream tasks that are not fixed. If this check box is selected and a task is completed early or late, Optiva automatically re-calculates Start and Due Date for all upstream tasks that are not fixed. |
Specify form security by role.
Form name | Privileges |
---|---|
FRMPROJECTMGMT | The project managers are the users who have
Form Security privileges to the Project
Management page of read/copy/write or read/copy/write/delete. The project managers have more control over the open tasks than the users who are assigned to the tasks. Only the project managers can change the start date, due date, duration, and assignment for all of the open tasks. Only project managers can skip tasks and recalculate the dates for the open tasks. Only project managers can unskip tasks. |
FRMUSERASSIGN | You must have at least read access to see
the Project
Management page. For the Assign Users to Task page, you must have at least read/copy/write privileges to:
|
button in the
Create at least one stage gate action set. Assign users or groups to the tasks and assign durations to each task.
Configure shop calendars, if necessary, for locations and users. A default shop calendar is provided in the system. See the Infor PLM for Process Application Configuration Guide.