Executing the search criteria
When you execute a search in the User Load page, the results are displayed in summary rows and details rows. The summary rows identify the users who meet the search criteria and their total load percentages for each date.
The detail rows show only the tasks (Action Lines) to which the user is assigned for the time period. Any tasks that fall outside of the date range are excluded from the results. The Action WIP IDs for each task are also shown in the results.
The comments show more information about the task. These comments were entered by the project manager in the Assign Users To Task page.
If the user is assigned to a parent task, only the child tasks are displayed in the Total Load tab. Parent tasks are hidden because they do not have durations and duration unit of measures.