Example for calculating hour duration tasks
This location calendar is used for the action set.
Standard Work Time | Work Time Overrides |
---|---|
Monday through Friday
|
11/5/2015 - 8:00 AM to 12:00 PM
11/9/2015 - Non-workday 11/11/2015 - 3:00 PM to 5:00 PM |
For tasks 1.1 through 1.4, only the location calendar that is assigned to the action set is used to calculate the task dates and times.
Task | Start Date and Time | Due Date and Time | Duration |
---|---|---|---|
1.1 | 11/2/2015 8:00 AM | 11/4/2015 5:00 PM | 24 hours |
1.2 | 11/4/2015 5:00 PM | 11/13/2015 10:00 AM | 32 hours |
1.3 | 11/13/2015 10:00 AM | 11/20/2015 10:00 AM | 40 hours |
1.4 | 11/20/2015 10:00 AM | 11/24/2015 10:00 AM | 16 hours |
- Task 1.1 has a start time of 8:00 AM; the actual work begins at 8:00 AM on 11/2/2015.
- Task 1.2 starts immediately after Task 1.1 is complete.
- For Task 1.2, the actual work begins on 11/5/2015. This is because the standard work hours end at 5:00 PM. The work time overrides are factored into the due date for this task.
- Task 1.3 starts immediately after Task 1.2 is complete.
- The work time overrides are factored into the due date for Task 1.3.
- Task 1.4 starts immediately after Task 1.3 is complete.
- Task 1.4 ends before the end of the day on 11/24/2015.
This table shows how the available work hours are calculated for each task.
Task | Date | Available Hours |
---|---|---|
Task 1.1
24 Hour Duration |
11/2 | 8
The actual work begins at 8:00 AM. |
11/3 | 8 | |
11/4 | 8
Task 1.1 ends at 5:00 PM. |
|
Task 1.2
32 Hour Duration |
11/5 | 4 |
11/6 | 8 | |
11/7 - 11/9 | Non-workdays | |
11/10 | 8 | |
11/11 | 2 | |
11/12 | 8 | |
Task 1.3
40 Hour Duration |
11/13 | 8
Task 1.2 ends. (2 hours spent on this task.) Task 1.3 begins. (6 hours spent on this task.) |
11/14 - 11/15 | Non-workdays | |
11/16 | 8 | |
11/17 | 8 | |
11/18 | 8 | |
11/19 | 8 | |
Task 1.4
16 Hour Duration |
11/20 | 8
Task 1.3 ends. (2 hours spent on the task.) Task 1.4 begins. (6 hours spent on the task.) |
11/21 - 11/22 | Non-workday | |
11/23 | 8 | |
11/24 | 8
Task 1.4 ends. (2 hours spent on the task.) There are 6 hours remaining in the day for the task that follows Task 1.4. |