Copying test plans from a project to a new formula

After you define a test plan for a project, copy the test plan to the formulas that you create on the Project > References tab.

  1. Select Project > References tab.
  2. Select Formulas from the Filter list.
  3. Click Create New Object.
  4. Specify the criteria in the Create New dialog. The PROJECT FORMULA PLAN rule code and copy method are provided by Infor.
    Create
    Enter a formula name and version.
  5. Click OK. The formula is created with the test plan from the project.