Completing the tasks
You can complete the tasks to which you are assigned from the Gantt tab:
Ahead of schedule
In this example, the task was completed ahead of the due date. The start date for the next task is adjusted to the current date and the Queue Status for that task changes to In Process Queue. The dates for the other open upstream tasks have not changed.