Unskipping steps in the Project Management page

Suppose you specified a step as skipped in the workflow. Now, you decide to reinstate that step to the workflow. In the Gantt tab, select the skipped step and click UnSkip task.

For a step to be eligible to be unskipped, all of these rules must apply:

  • The step must have a Queue Status of Ignore and a Rcv Ind of Skip.
  • The Queue Status cannot be Ignored – Locked.
  • The step when skipped, must not have caused other tasks to be skipped or completed.
  • The step must not have entries in the Next Lines column that are already in progress or complete.

What if the skipped step is not eligible to be unskipped? In this scenario, insert a step immediately after the skipped step. Then, specify the same criteria as the original step.