Example: Production Schedule Complete Transactions
Shop Floor Control Parameters:
PS Look Ahead : 7 Days
PS Look Behind: 0 Days
Note:  By setting 
 these values to seven and zero, we instruct the system to work against 
 weekly production schedules and provide weekly production performance 
 reports.
      Original production schedule with original release dates and released quantities:
Schedule ID: ABC123
Item: FA-10000
| Date | Released | Completed | 
|---|---|---|
| 6/07/07 | 100 | 0 | 
| 6/14/07 | 100 | 0 | 
| 6/21/07 | 100 | 0 | 
Actual production dates and quantities to be posted:
| Trans Date | Completed | Release Date Posted Against | 
|---|---|---|
| 6/03/07 | 50 | 6/07/07 | 
| 6/07/07 | 43 | 6/07/07 | 
| 6/08/07 | 20 | 6/14/07 | 
| 6/12/07 | 75 | 6/14/07 | 
Result of posting the above transactions is:
Schedule ID: ABC123
Item: FA-10000
| Date | Released | Completed | 
|---|---|---|
| 6/07/07 | 100 | 93 | 
| 6/14/07 | 100 | 95 | 
| 6/21/07 | 100 | 0 | 
Note:  Production 
 schedule completed quantities will not appear as completed unless they 
 are posted against the last operation of the production schedule routing. 
 At that time, the appropriate backflushing and costing transactions will 
 also occur.