You can use the Engineering Workbench to add a routing 
 and bill of material to inventory items (the current routing), production 
 schedules, jobs, or estimate jobs. If you're using the Molding Pack, you 
 can also add a routing and bill of material to co-product jobs or co-jobs.
       
      - 
            To select the transaction: 
	
            
               - 
                  In the View field, select the 
		 type of routing/BOM to work with.
               
- 
                  Click the filter button in the toolbar.
               
- 
                  Use the header fields to select the item, job, or production 
		 schedule to which you want to add routing/BOM information.
               
- 
                  Click the filter button again. Any existing routing information 
		 for the item, job, or schedule is displayed.
               
 
- 
            To create the routing: 
	
            
               - 
                  In the Operations grid, add a new record for each new operation 
		 in the routing. Use the grid fields to select a work center and 
		 define operation setup, queue, and run times, as well as the start 
		 and end date and other information about the operation.
               
- 
                  After adding all the operations for the routing, select .
               
- 
                  If you need to define resources for an operation beyond the 
		 default resource group defined for that operation's work center: 
		 
		
                  
                     
                        - Right-click on the operation number in the Operations grid 
			 and click Details. The appropriate 
			 Operations form opens, with the record for this operation 
			 displayed.
- In that form, select the Resources 
			 tab and define the crew or machine resource groups that this 
			 operation requires in order to be processed, as well as parameters 
			 related to the resource groups.
- Save the record and close the form.
 
 
- 
                  If you need to define costs for an operation: 
		
                  
                     
                        - Right-click on the operation number in the Operations grid 
			 and click Details. The appropriate 
			 Operations form opens, with the record for this operation 
			 displayed.
- In that form, select the Costs 
			 tab and define the values used in costing this operation.
- Save the record and close the form.
 
 
 
- 
            To add materials: 
	
            
               The Engineering Workbench record containing 
	 a new operation must be saved before you can add materials for the 
	 operation. 
 
               - 
                  In the Materials grid, add a new record. Select an operation 
		 for which you want to define a material. Then select or enter 
		 the rest of the information about the material. You can add multiple 
		 lines defining different materials for a single operation.
               
- 
                  Once you have added all the materials for the operations you 
		 defined, select  to 
		 save the new materials.
               
 
         You can now viewing the new routing/materials in the left tree pane 
 of the Engineering Workbench form. The pane 
 contains a tab for each of the available routing/Bills of Material.
         To see the new operations or materials you added, either close and reopen 
 the Engineering Workbench form, or click 
 the filter button on the left pane and click OK 
 in the dialog that appears. Either method refreshes the tree pane.
         The tree display is shown here:
         
             
         
         You can collapse the tree display into a simpler view 
 by selecting the (-) symbol next to each item or operation. For example, 
 suppose you want to look at operations for the item, without displaying 
 the materials. Click the (-) symbol next to the operation, and the materials 
 disappear in the collapsed tree. The word "Alternate" appears 
 next to any material that is specified as an alternate material on a current 
 operation.
         Note:  You cannot 
 add or remove operations or items from routing/BOMs in the left pane. 
 Use the right pane of the Engineering Workbench 
 form for maintaining routing/BOMs.