Using the Estimation Worksheet
The Estimation Worksheet form shows all estimate jobs that reference existing estimate order line items. You can use this form to modify the costs to produce each job's items.
- Open the Estimation Worksheet form and specify a job.
-
In the Estimation section, specify this information:
- Estimate
- Select the estimate number.
On the classic form, select this value in the Order Ref field.
- Estimate Job
- Select the estimate job number.
On the classic form, select this value in the Job field.
- Co-product Mix
- Select the co-product mix number or name.
- Vendor Price Breaks
- This field is enabled if the specified job uses an item with
materials for which vendor price breaks were entered.
Select this check box to apply the price breaks to the worksheet.
-
In the Items section, specify this information:
- Qty Ordered
- Specify the number of items to order.
- Calculation
- Select one of these options:
- Extended Cost/Unit + Percentage: Adds a percentage of the original extended cost, as displayed in the Cost/Unit field, to the original extended cost.
- Extended Cost/Unit + Dollar Amount: Adds a flat domestic currency amount to the extended cost, as displayed in the Cost/Unit field.
- Set Fixed Net Price/Unit: Uses the fixed net price per unit, without the original extended cost.
- Use Group Markup: Adds a percentage to each costing element.
- Use Discounted Unit Price: System automatically calculates the net prices using the unit price amount.
On the classic form, select this value in the Price Basis field.
- Calculation Value
- Specify the amount applied to the basis formula.
On the classic form, specify this value in the Estimate Worksheet field.
- Discount %
- Specify the percentage discount applied to the order.
On the classic form, specify this value in the Sales Discount field.
-
If you select the Use Group Markup
calculation, in the Group Markup section, perform these steps:
- Specify the percentage markup for each costing element.
- To update the record with the new markup, click Apply Markup.
- To reset all Group Markup fields to zero and update the grid, click Clear Markup.
- To recalculate the unit cost, click Reprice.
-
To apply the costs to the job BOM, click Update Job Matl Cost.