Microsoft Project Integration
The Windows client can import and export project task data to and
from Microsoft Project. If you have Project installed on your local computer, import and
export buttons appear on the Project Tasks form.
Note that the SyteLine web client supports import/export integration with Microsoft Project Online.
This information is exported:
- Project name and number
- Project tasks
- Project Resources
- Predecessor tasks
- Resource names
- Duration
- Start date
- Finish date.
The system supports two MS Project calendar types:
- 8 hour: 8:00am to 5:00pm, Monday through Friday.
- 24 hour: 24 hours a day, seven days a week.
When you open the Project Tasks form, the system analyzes at the Default Shift Calendar. If the calendar includes hours outside of the standard 8:00am to 5:00pm range, then it tells MS Project to use a 24 hour calendar.