Actual G & A Cost
The actual G & A cost is the amount of G & A cost generated when the milestone is nominated. On the Estimate Revenue Milestones and Revenue Milestones forms, the Actual G & A Cost field is in two places: on the General tab and on the Audit tab.
On the Estimate Revenue Milestones form, the Actual G & A Cost field is always blank because costs are not generated for estimate projects.
On the Revenue Milestone Nomination form, the Actual G & A Cost displays from the Revenue Milestones form, but you can override the amount.