Due Date

On the Items tab, enter the date that the line/release is due to be received. The date does not have to be the same on all line/releases for a purchase order. A PO line/release should be received by this date, or it is considered past due.

On the Planning tab, the system calculates the due date by subtracting the item's dock-to-stock lead time from the operation's start date, if not blank, or the job's start date if the operation's start date was blank.

Note:  The due date must be a valid manufacturing day. The manufacturing day (or MDAY) calendar is a list of valid manufacturing days between the MDAY Start and MDAY End date fields on the Planning Parameters form, using the default scheduling shift and Holiday definitions to generate the list.