Labor

If the work center is not an outside work center, the Setup and Run Labor Costs are calculated as follows:

Setup Costs

[WCSR * JRSH * (100/WCE)] / ILS = SC

  • SC = setup cost
  • WCSR = work center set up rate
  • JRSH = job route setup hours
  • 100/WCE = 100 divided by work center efficiency
  • ILS = item lot size

Run Costs (Lbr)

WCRR * JRRH * (100/WCE) = RC

  • RC = run costs Lbr
  • WCRR = work center run rate Lbr
  • JRRH = job route run hours Lbr
  • WCE = work center efficiency