Expected Receipt Date

If you do not have a specific PO to expedite, specify the date on which you expect to receive the purchased item. If you are using a PO, specify the PO due date.

If you do not specify a date, the APS system functions as if the item does not have a lead time for this demand. This makes the item non-blocking for the order/job. When this occurs, the Projected Date field shows the date on which APS determined the item would be needed. This value is useful when creating a corresponding PO.