BOM Sequence
Enter the sequence which the current material should display on a material list or single-level bill of material. This field is optional. If you enter a value, the next time you add a material for the job or production schedule, the default will be that value plus 1.
The bill of material sequence number can be a useful mechanism for tracking and reporting on material. It is used on these reports:
- Indented Current BOM Report
- Single Level Current BOM Report
- Estimate Job Indented BOM Report
- Estimate Job Routing Report
- Job BOM Report
On the BOM Import Builder form, this field displays the BOM sequence. You cannot update this field.