Cross-Referencing a Job Material to a Purchase Order
Use the Job Materials form to cross reference a job material to a purchase order.
- On the Job Materials form, add a new material or select an existing one.
- Select the Source tab.
- Make sure Purchase Order is selected in the Source field.
- To cross-reference the job material to an existing purchase order, specify the PO number in the unlabeled field next to the Source field. In the second unlabeled field, specify the PO line number (or leave it blank to create a new line on this PO).
- Save the record to enable the button.
- Click the Source field. button. The system creates a purchase order and purchase order line that is cross-referenced to the job material and inserts the PO number into the
- Optional: You can click again to display the cross-referenced purchase order line.
To create a new purchase order and assign a particular PO number, specify the PO number. To create a new purchase order and allow the system to assign a PO number, leave the field blank.
Note: You can cross-reference
to a range of purchase orders using the Material Planner Workbench form.
After a cross-reference is created, you can change it by either removing the line item or changing the cross-reference information, thus deleting the cross-reference. When this happens, the system displays a warning message indicating the cross-reference will be unlinked.
To view unlinked references, you can filter on the Unlinked Reference check box. You can then do one of the following:
- Clear the Unlinked Reference check box so that the record is no longer unlinked. There is no indication in the system that the record was ever cross-referenced.
- Delete the supply record.
- Leave the Unlinked Reference check box selected.