Firming MPS Orders
This process describes how to convert MPS receipts into jobs or production schedules. The system converts the MPS receipt depending on the Production Type setting on the Items form.
Production Type | Converts To |
---|---|
Job | Job-Firm |
Prod Sched | Routes to Generate Production Schedules form and creates production schedules |
Kanban/Jit | Prevents you from firming order |
Note:
- If a job is to be created, you enter the job number and the quantity of the release, and the system creates the job header automatically. However, you must copy or create the routing and bill of material.
- If a production schedule is to be created, the system takes you to the Generate Production Schedules form.
To use this feature, follow these steps:
Note: You can also use the Material Planner Workbench to firm MPS
receipts.