Approving an ECN

You can approve an ECN at the individual item level or at the header level. If all ECN line items have been approved, approve the ECN at the header level. If the statuses of the ECN line items vary, you must approve at the individual line item level. You must "Approve" or "Not Approve" an ECN before you can post it.

See these topics:

  • Approving an ECN at the Item Level
  • Approving an ECN at the Header Level
Related topics
  • Engineering Change Notice Steps
  • Working with ECNs
    • Engineering Change Notice Steps
    • Creating an Engineering Change Notice Header
    • Creating an Engineering Change Notice Line Item
    • Approving an ECN
      • Approving an ECN at the Item Level
      • Approving an ECN at the Header Level
    • Posting an Engineering Change Notice