Completing a QA Process
- Open the QA Process Phase Activities form.
- For each completed activity, specify who completed it, and when it was completed.
- Save the record and close the form.
- Open the QA Process Phases form.
- If all activities in a phase are complete, specify who completed the phase.
- Select Complete.
- Save the record and close the form.
- Open the APQP Processes (QA Processes) form.
- When all phases are complete, specify who completed the process, and the date on which it was completed.
- Select Completed.
- Save the record and close the form.