Planner Trace Level

Specify the level of trace messages to be written while the APS Planner is executing. The table below shows the four trace levels available along with the trace flags that are enabled at each level: Minimal, Limited, Extensive, and Full.

Trace Level Trace Flags
Minimal Startup + Warnings
Limited Startup + Warnings + Order + BOM + Item + Supply Switching
Extensive Startup + Warnings + Order + BOM + Item + Event + Supply Switching
Full Startup + Warnings + Order + BOM + Item + Operation + Final Resource + Event + Supply Switching + Time Fence
Note: Increasing the trace level from Minimal may cause the APS Planner run time to increase, and should only be done based on a recommendation from Infor.

Default: Minimal