Planner Trace Level
Specify the level of trace messages to be written while the APS Planner is executing. The table below shows the four trace levels available along with the trace flags that are enabled at each level: Minimal, Limited, Extensive, and Full.
Trace Level | Trace Flags |
---|---|
Minimal | Startup + Warnings |
Limited | Startup + Warnings + Order + BOM + Item + Supply Switching |
Extensive | Startup + Warnings + Order + BOM + Item + Event + Supply Switching |
Full | Startup + Warnings + Order + BOM + Item + Operation + Final Resource + Event + Supply Switching + Time Fence |
Note: Increasing the trace level from Minimal may cause
the APS Planner run time to increase, and should only be done based on a
recommendation from Infor.
Default: Minimal