Fixed Lead Time Reduction (Hours)
Enter the number of hours that an item's standard Fixed Lead Time (see “Items - Fixed Lead Time” for more information) will be reduced in the APS plan. This parameter applies to all items.
Note: The standard Fixed Lead Time value is expressed
in days on the item record. The APS planning functions interpret lead
time in hours. So, if the Fixed Lead Time on the item record is 3 days
(72 hours), and you want to reduce it to 1 day, enter a value of 48 in
the Fixed Lead Time Reduction field to reduce the value by 2 days. When
you run the APS Planning activity, the system interprets the fixed lead
time value as 24 hours when calculating the release date of the planned
order.
The system applies this value only if the appropriate Use Expedited Lead Time parameter is enabled.
Default: 0 hours