Pull and Push Planning
The APS planning process employs a strategy where the orders are all ranked by Order Priority and processed one-by-one through the algorithm. The system will pull plan the order first. As the order is being “pulled” through time, if the order crosses the “Current Time” threshold, the pull stops and a push pass ensues. After the push, the order is then pulled from the projected date to remove slack.