Items - Phantom Flag
Select the check box to designate this item as a Phantom.
When you run the APS Planning activity, the system bypasses the phantom item and creates planned orders only for the material components in the phantom item's current bill of material.
The system plans items differently based on the combination of how you set the Phantom Flag, Accept Requirements, and Pass Requirements fields on the Planning Parameters form.
See “Items - Accept Requirements” and “Items - Pass Requirements” for more information about the relationship between these fields.