Apply Order Maximum Through BOM
Select this field to apply order maximums to sub-levels of the BOM. Clear this field to restrict order maximums to the end item of a demand.
EXAMPLE: A wheel is made up of one hub (plus other items). The maximum order size for hubs is 5. A job is created for 10 wheels. If this field is selected, the production of hubs is planned in two blocks of 5 each. If this field is not selected, the entire production of hubs is planned in one block of 10, despite the order maximum.
Default: Do Not Select