How the break rule affects reallocation
The operation's Break Rule (JS19VR.CRSBRKRL) affects how the Planner can reallocate resources to interrupted operations. The table below describes the Break Rule options and how they affect reallocation.
Break Rule | Description |
---|---|
0 (Cross shifts only) | The operation can only be planned within a block of time in which the only interruptions are off-shift periods. If a given block of time is interrupted by the resource working on other jobs, the operation will not be planned in that block of time. |
1 (Cross shifts and other orders) | The operation can be planned within a block of time that is interrupted either by off-shift periods or by other demands already planned. |
2 (No breaks) | There must be a large enough block of uninterrupted time on the associated resources for the operation to be completed (if the Planner cannot find an unbroken block of time, the job will be blocked). |