Creating a new multiple project task with Microsoft Project Client

  1. Specify Task 2 and Task 3 on the Microsoft Project Client.
  2. Click Sync Out on the toolbar, and then click Yes at the prompt.
    The Sync Out process creates two new tasks in SyteLine and returns the Task Numbers.
  3. To verify the task number, select Task 2, and then click AssignSyteLine Resource. The task number shows the new number created in SyteLine.
  4. To verify the new project tasks in SyteLine, open the Project Tasks form in SyteLine and filter for the project number created in the first step.