Scheduling a process to run in the background
- In a utility or activity form, set your selection criteria and task options.
 - If your selection criteria include dates and you are scheduling the process to run periodically, you must increment the date.
 - From the Actions menu, select Background.
 - 
            In the 
			 Frequency field of the 
			 Background Queue form, select an interval to use
			 as a time unit in scheduling. 
		  
            
If you select Weekly, for example, you can subsequently specify that the process runs every third week.
To run a process one time only, select Daily.
 - 
            Depending on the 
			 Frequency setting, use the
			 appropriate tab to set times and dates based on the frequency. 
		  
            
-  
				                 Daily tab: To run the
				  process one time only, you must specify 
				  Occurs > Once At. 
				  
To run the process at least once every day, you must specify Occurs > Every.
 - Weekly tab: Specify the number of weeks in the interval, the day of the week on which to start the process, and the time of day.
 -  
				                 Monthly tab: To run the
				  process on a specified date of each month, such as the 15th of each month,
				  select 
				  Occurs > On Day. 
				  
To run the process on a specified day of the week, such as the first Tuesday of each month, select Occurs > On.
 
 -  
				                 Daily tab: To run the
				  process one time only, you must specify 
				  Occurs > Once At. 
				  
 - 
            
Click OK.