Resource Plan

This form is used only with the APS planning mode. Use this form to view details about the work the APS system has planned to be processed by a specific resource. This work may be a job, production schedule, or master production schedule (MPS), if it represents user-defined production, or it may be a planned order (PLN), if the system generated the activity from another demand (such as a customer order, forecast, etc.). In the case of a PLN, the Parent Reference field displays the identifier of the demand that generated the PLN.

To view the sequence of all planned work for a particular resource, select the resource to analyze in the Resource field and then click the filter button to display the records. In the grid view, the records are displayed in the sequence the activities are planned to move through the resource.

This form displays all work occurring between the time the Planning activity was last run and the end of the Plan Horizon.