Production Exceptions Report

Use this report to display a range of demands that are late within the Days Late threshold you specify. The due date, projected completion date (that is, the Scheduled date for the demand), and number of days late are displayed. Use the Schedule Types fields to select the types of demands for which to display this information.

The Days Late value is calculated by subtracting the demand's End Date from its Projected Date. The Projected Date is calculated by the Scheduler as the projected completion date of the demand. The MRP or APS planning activity calculates the End Date.

Select the Show Detail field to display the operation that was responsible for making the demand late, along with the number of days the operation (and all of its required resource groups) waited. The Days Waited value is calculated by subtracting the date/time the operation started to wait from operation's Start date/time.