Item Bottlenecks Report APS

This form is used only with the APS planning mode. The report displays each purchased item's lead time and the number of demands that are delayed due to shortages of the item. This Delayed Demands count is calculated as the number of late demands for which the item is on the critical path and the demand had to wait for the item to be received.

Select the List Delayed Demands field to include details of each delayed demand on the report, including the number of days the demand had to wait for the item to be received and the number of days past the due date the demand will be available.

The report output is sorted by planner code, delayed demands, and then item.