Use Offset Hours

This field applies to APS and the Scheduler. MRP uses offset hours indirectly if you use the Lead Time Processor utility with the Use Offset Hrs option selected.

Select the box to allow this operation to start before the previous operation completes. Then, in the Offset field, enter the number of hours this operation must wait to start after the previous operation starts.

When you accept the default value of cleared, this operation begins at the ending date and time of the previous operation.

See About Overlapping Operations for more information.