Split Size

This field applies to the Scheduler only.

Specify the multiple for splitting the job operation quantity during an operation overlap or operation splitting situation. Or specify 0 to disable operation splitting.

For example, if you have an operation quantity of 50 and the Split Size is 10, the quantity may be processed in five loads of 10 items.

When the Scheduler processes an operation that can be split, it divides the quantity up into loads according to the Split Size and allows multiple resources from the resource group to process them (according to the resource's selection rules). After all loads are completed, the Scheduler recombines them into one quantity.