Low Level Code

Enter the lowest level at which this item appears in the indented bill of material for the Finish job of this job order. A value of 0 indicates the item is the final item, or the finished good. The system supports up to 20 levels of low-level coding.

For estimate job orders, this field is set when you run the Estimate Job Bill Of Material Processor. For job orders, this field is set when you run the Job and PS Bill of Material Processor. Run the Job and PS Bill of Material Processor and Estimate Job Bill of Material Processor after you run the Current Bill of Material Processor.

On the Component Shortages APS and Component Shortages Report APS forms, this read-only field shows you at what level in the BOM the selected material resides.