Job Reschedule Tolerance Factor - In/Out

Note:  The values entered in these field are overridden by the values set in the Product Codes form. To retain the values that are set on this form, leave the field blank for these values on the Product Codes form.

For APS Planning:

  • In the In field, enter the number of days earlier than the current due date that the job needs to be rescheduled before the system generates the Cross Reference Special Receipt: Reschedule 99/99/99 exception message.
  • In the Out field, enter the number of days later than the current due date the job needs to be rescheduled before the system generates the Cross Reference Special Receipt: Reschedule 99/99/99 exception message.

For MRP Planning:

  • In the In field, enter the number of days earlier than the current due date that the job needs to be rescheduled before the system generates the Move Out Receipt exception message. For example, if the In field is set to 9, and the job receipt is scheduled to be available 10 days before the demand is due, no exception message is generated; however, if the In field were set to 10, the Move Out Receipt exception would be generated.
  • In the Out field, enter the number of days later than the current due date the job needs to be rescheduled before the system generates the Move In Receipt exception message.