Copy Indented BOM

Select Yes to create sub-jobs cross referenced to the end-item job and to copy the bill of material to those sub-jobs. The activity will create a sub-job for any current subassembly material within the BOM that has a Reference of Job. The sub-job uses the prefix of the end-item job. When you first create the sub-jobs in this manner, the Start and End dates are populated based on lead time offsets. If the Preserve Pre-Released Production Dates field is not selected on the Planning Parameters form or on the Job Orders form, the system resets the Start and End dates each time you run the MRP or APS Planning activity.

Accept the default of No to copy a single level of the BOM.

Note:  You can view the parent-child relationship between jobs and sub-jobs on the Job Orders form on the References tab.