Close Job

Enter whether or not you wish to close the job after posting this transaction. This field appears only when goods are being moved to stock.

When the item is Actual-costed, the system calculates the unit cost of the completed goods, as charged to inventory, differently based on the setting of this field and based on the setting of the Costs Based on Complete shop floor control parameter:

Close Job field selected? Costs Based on Complete setting Job finish cost equals...
Yes n/a (job's WIP Total - job's WIP Complete) / quantity being moved
No Job Planned unit cost for the job. The system calculates this value by summing each operation's setup, labor, and machine hours and rates, overhead rates, and efficiencies, as well as each material's planned cost, scrap factor, and quantity per assembly.
No Operation Sum of complete operations' actual costs and open operations' planned costs. The actual cost used for a completed operation is based on the value in the operation's WIP amount.
Note: 
  • If the Job Stock Trx field on the Shop Floor Control Parameters form is cleared, the Move to Loc and Lot fields cannot be updated. The Job Stock Trx field must be selected before any inventory transactions can be performed.
  • When the item is Standard-costed, it is always moved into inventory at its item master standard unit cost at the time of the move, regardless of what cost has been posted against the job or how the job has been processed.