Calculate Job End Dates When Blank

By default, SyteLine initializes sub-job start and end dates using the Lead Time Processor. By leaving the sub-job dates blank, the dates for firmed, and released, sub-jobs can be initialized by APS planning using backward planning from the need date. The Job Orders form will only allow blank start and end dates for firm sub-jobs if this parameter is selected. In all instances where SyteLine would automatically populate start and end dates using lead time, the fields for firm sub-jobs will be left blank when the For Firm Sub-Jobs parameter is selected.

The For Released Sub-Jobs parameter controls released sub-job dates, and is only available if the Calculate Job End Dates When Blank: For Firm Sub-Jobs field is selected.