Copying from Another Production Schedule

To copy a production schedule and its releases and create a new Planned production schedule, follow these steps:

  1. Open the Copy Production Schedules form.
  2. Enter the appropriate data in the required fields.
    • In the From and To Schedule ID field, enter the range of production schedule IDs from which to copy routing information.
    • In the Starting and Ending Item fields, enter the range of items to copy; leave the fields blank to copy all items.
    • In the Starting and Ending Date fields, enter the range of dates to create release lines for.
  3. When finished, click Process.