Creating a manual data lake queue

  1. Select Admin > Data Lake Queue. The Data Lake Queue Setup screen is displayed.
  2. Click New. The Ranges screen is displayed.
  3. Specify the date range to perform bulk ingestion of the records created during the specified period.
  4. Click Next. The Options screen is displayed.
  5. Select the required tables in the Tables to Extract field to perform bulk ingestion of the records created in the selected tables.
  6. Specify the period (in days) in the Days to Extract field to perform bulk ingestion of the records that are created during the specified period.
    Note: The value specified in this field is prioritized over the date range for bulk ingestion.
  7. Click Save. The bulk ingestion record is added to the data lake queue.