Receiving components
The material received in the kit build department contains a work in process status.
- From the RF Work Center Main Menu, select .
- Scan the stage-in location the material was moved to from the storage locations.
- If you are receiving by item, use the keys to select a pallet. Scroll to the right to verify the lot number, if required.
- Verify the item and quantity, and then specify Yes.
- Scan the pallet that contains the material being received.
- Repeat steps as needed to receive components into the kit build department.
- Use the back button in the RF browser to return to the Work Center Main Menu.