Sales Entry Generate Service Orders Assembly Report ranges and options
Ranges
Options
- Whse
-
Specify the ordering warehouse of the orders to include on the report.
- Enter a List of Order #'s
-
Select Yes to enter a list of orders to include on the report. Click , then use the Order field to add orders to the list. You are not required to list the orders sequentially. Click when you are done.
Each order that you specify is validated by the system and must meet these criteria:
- It must be in Stage 1-Ordered or Stage 2-Picked.
- It must be an assembly order.
- It cannot be tied to a service order.
- It cannot be suspended.
If you specify a list of orders, any ranges that you specified are ignored.
- Print Order thru Promised/Requested Date
-
This option works in conjunction with Days to Allow Forward and Print on Requested Date? options.
Note: Promised dates for line items are not considered when sales orders are evaluated for processing eligibility.Specify the promised date or requested date of the orders to include on the report. Orders with a promised or requested date that is earlier than the specified date are also included on the report. To use the current date, leave the default value of **/**/**. To include orders with dates that are up to a week earlier than the current date, specify -1 through -7 as the day in the default value. For example, if you specify **/-7/**, the current date less seven days is used as the date. To include all orders that otherwise qualify for the report, specify 12/31/49.
- Days to Allow Forward
-
Specify a value up to 999 to include orders with a promised or requested date that is later than the date in the Print Order thru Promised/Requested Date option. For example, if the current date is April 1 and you specify 14 in this field, all qualified orders with a promised or requested date of April 1 to April 15 are in included on the report.
- Print on Requested Date?
-
Select Yes to include orders on the report, based on the requested date. Select No to include order on the report, based on the promised date.
- Ordered Stage: (O)rdered, (P)icked, (B)oth
-
Indicate the stage of the orders to include on the report.
- (S)ummary/(D)etail
-