Moving a Report Scheduler job to a different queue

If you move a job to a different queue, the run date and time of the job does not change.

  1. Select Report Scheduler > Administration > Activity.
  2. Specify the search criteria, and then click Search.
  3. Select the one or more jobs, and then click Change Queue.
  4. Specify the queue.
  5. Click OK.