Changing the run date and time of a print job

  1. Select Report Scheduler > Administration > Activity.
  2. Specify the search criteria, and then click Search.
  3. Select the one or more jobs.
  4. Select More . . . > Change Run Date/Time.
  5. Specify the new run date and time. The date must be equal to or greater than the current system date.
  6. Optionally, select Change Schedule Type, and then select a schedule type.
  7. Click OK.