Example 2: Scrap Transactions - Costing

Operation Control Point Qty Complete Qty Scrap
10 No 5  
20 No 5  
30 Yes 5  
40 No 5  
50 No   5
60 Yes    

In contrast to production schedule complete transactions, which you record at control points, you report scrap transactions at any operation. In the above example, assume that you reported a quantity of 5 as complete for Operation 30. If you reported a quantity of 5 as scrapped at Operation 50, the system would also backflush for Operations 40 and 50. The system would not scrap 5 or backflush for operation 30 (or prior to it), because it is a control point.

However, the system would calculate the accumulated WIP costs of the scrapped materials for all operations, 10 through 50 inclusive, and move them to the Scrap Expense account.