Completing Multiple Activities Individually

To complete multiple activities individually:

  1. On the Activities view, select the activities you want to complete, and in the Task Pane Common Tasks area click theComplete Activity link.
  2. In the Result field select an item from the list.
  3. In the Note field, specify any information that you want to be added to all of the activities you are completing.
  4. Click Individually.
  5. If any of the selected activities are recurring, and you are prompted, select Complete this Occurrence or Complete all Occurrences, and then click Continue.
  6. Follow the remaining steps for completing each activity until each activity has been completed.