Running a training quest
You must save and run the training quest to receive output results from the applied activities. When the training quest is running, the status of the quest, and the progress of each separate activity in the flow is displayed. Each separate activity status is traceable when configuring and running the quest.
A quest can be run completely or partially. A partial run, for a selected activity, is available to view the output of a specific activity in the flow. If the quest has been run previously, the activities preceding the selected activity are not rerun. Therefore, running time is shorter. The previous activities must have been run successfully.
These statuses are displayed on the activity box:
Description | Image | Meaning |
---|---|---|
None | n/a |
Activity not yet run or was run and settings were changed. Activity has no error based on validation. |
Error |
Activity is not connected. Activity is not configured properly. |
|
Queuing | Activity is awaiting to be executed. | |
Running | Activity is in running state. | |
Failed | Activity was executed, but failed. | |
Finished | Activity was successfully executed. |
To run a training quest:
- Select a quest.
- Save the quest.
- Click .
- After the activity completes successfully, click the output port of the activity to display the output results.